Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2026 | COT - LCBU - Building Final | Re-inspection required | 6/18/26: ADA REQUIREMENTS must be met at 8 units per IBC 1108.6.1.1, electrical outlets required throughout per IEBC 1007.4, anti-tip must be properly installed at every unit, properly secure. NM-cable at counter, listed cover required at j-box. | |
| 08/03/2026 | COT - LCBU - Building Final | Not Ready | Building 5. Unit 109. Remove door from closet with sub panel. Complete panel schedule at sub panel. Add receptacle due to spacing over 12’. Coat hanger shall be at 48”. Mirror shall be at 40” to the reflective side. Ensure all flush valves are on the open side at all ADA bathrooms. Unit 100 missing receptacle near door entry. Lav greater than 34” coat hanger shall be at 48”. Mirror shall be at 40” Receptacle near kitchen counter shall be GFCI protected. Remove pan head screws from sub panel covers. |
|
| 08/18/2026 | COT - LCBU - Building Final | Partial Pass | 8/18/2026 Partial pass. Okay to apply for level 4 TCO for all units. pending for the corrections to be made for the type 1r electrical panels. |