Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2026 | COT - HCBU - Preslab | Passed | ||
| 04/21/2026 | COT - HCBU - Preslab | Partial Pass | Partial pass for south east exterior wall | |
| 04/23/2026 | COT - HCBU - Preslab | Partial Pass | Partial pass for south east exterior wall 4.23.26 Partial pass; service express West End of building from Z-W. Also Pending revision for W-V on the west end of service. Missed the footer on the north end of the building needs to be trenched. |
|
| 04/28/2026 | COT - HCBU - Preslab | Partial Pass | ||
| 05/08/2026 | COT - HCBU - Preslab | Partial Pass | 5/8/2026 Partial pass for: North East side (jeep showroom) F3, double mat, f40, f80, f100, f40(2), f74, f60, f64-okay for concrete placement. Note: submit 3rd party report on f80 footing located at northwest corner. |
|
| 05/11/2026 | COT - HCBU - Preslab | Partial Pass | Partial pass interior footing reinforcement | |
| 05/14/2026 | COT - HCBU - Preslab | Not Ready | ||
| 05/15/2026 | COT - HCBU - Preslab | Partial Pass | 5-15-26: Footings at G/L-J95-5.2 & 6 require Engineer RFI & footings at G/L -I1-6-6.1 are not per plans. Excavation/Reinforcement at Service Drive: G/L -J3 & J7/5.2 verified per plans and okay for concrete placement. | |
| 05/26/2026 | COT - HCBU - Preslab | Partial Pass | 5/26/26 Footings for CDRF northwest showroom, and service drop off. |
|
| 06/04/2026 | COT - HCBU - Preslab | Partial Pass | 6/3/26: Pre-slab approved at NorthWest corner of project NVD addition | |
| 06/06/2026 | COT - HCBU - Preslab | Partial Pass | 6-6-26: reinforcement/excavation at Jeep Showroom approved. Okay for concrete placement from G/L: G.1-J.4/0.9-2.9. | |
| 06/08/2026 | COT - HCBU - Preslab | Canceled | 6-8-26: canceled by contractor. | |
| 06/09/2026 | COT - HCBU - Preslab | Partial Pass | 6-9-26: reinforcement/vapor barrier at slab on grade for service entrance approved. Okay for concrete placement. | |
| 06/12/2026 | COT - HCBU - Preslab | Partial Pass | 6-12-26: footing reinforcement/excavation verified per WF-20 at west end of express building. Okay for concrete placement. | |
| 07/24/2026 | COT - HCBU - Preslab | Partial Pass | 7-24-26: dowels at jeep showroom pourback approved ( 2 sections). Pre slab/reinforcement & excavation for mezzanine at parts areas verified per footing schedule -F24 & S680/8 & S604/42. Okay for concrete placement at progress areas. | |
| 08/05/2026 | COT - HCBU - Preslab | Partial Pass | 8/4/26: pre-slab at express service shop west half approved | |
| 08/07/2026 | COT - HCBU - Preslab | Partial Pass | 8.7.26 Express building:break room,parts room, and bathroom. |
|
| 08/20/2026 | COT - HCBU - Preslab | Partial Pass | 8.20.26 Women's bathroom toilet relocated; men's bathroom sawcuts, hallway sawcut and break room drain connection. |
|
| COT - HCBU - Preslab | Scheduled |