Permit: TC-COM-0525-01025

Parcel: 13014023A


Addresses:

4220 E 22ND ST

Inspection Status: Passed

Inspection History: COT - HCBU - Preslab  

Date Description Inspector Results Comments
04/15/2026 COT - HCBU - Preslab   Passed
04/21/2026 COT - HCBU - Preslab   Partial Pass Partial pass for south east exterior wall
04/23/2026 COT - HCBU - Preslab   Partial Pass Partial pass for south east exterior wall

4.23.26
Partial pass; service express West End of building from Z-W. Also Pending revision for W-V on the west end of service. Missed the footer on the north end of the building needs to be trenched.
04/28/2026 COT - HCBU - Preslab   Partial Pass
05/08/2026 COT - HCBU - Preslab   Partial Pass 5/8/2026
Partial pass for:
North East side (jeep showroom)
F3, double mat, f40, f80, f100, f40(2), f74, f60, f64-okay for concrete placement.
Note: submit 3rd party report on f80 footing located at northwest corner.
05/11/2026 COT - HCBU - Preslab   Partial Pass Partial pass interior footing reinforcement
05/14/2026 COT - HCBU - Preslab   Not Ready
05/15/2026 COT - HCBU - Preslab   Partial Pass 5-15-26: Footings at G/L-J95-5.2 & 6 require Engineer RFI & footings at G/L -I1-6-6.1 are not per plans. Excavation/Reinforcement at Service Drive: G/L -J3 & J7/5.2 verified per plans and okay for concrete placement.
05/26/2026 COT - HCBU - Preslab   Partial Pass 5/26/26
Footings for CDRF northwest showroom, and service drop off.
06/04/2026 COT - HCBU - Preslab   Partial Pass 6/3/26: Pre-slab approved at NorthWest corner of project NVD addition
06/06/2026 COT - HCBU - Preslab   Partial Pass 6-6-26: reinforcement/excavation at Jeep Showroom approved. Okay for concrete placement from G/L: G.1-J.4/0.9-2.9.
06/08/2026 COT - HCBU - Preslab   Canceled 6-8-26: canceled by contractor.
06/09/2026 COT - HCBU - Preslab   Partial Pass 6-9-26: reinforcement/vapor barrier at slab on grade for service entrance approved. Okay for concrete placement.
06/12/2026 COT - HCBU - Preslab   Partial Pass 6-12-26: footing reinforcement/excavation verified per WF-20 at west end of express building. Okay for concrete placement.
07/24/2026 COT - HCBU - Preslab   Partial Pass 7-24-26: dowels at jeep showroom pourback approved ( 2 sections). Pre slab/reinforcement & excavation for mezzanine at parts areas verified per footing schedule -F24 & S680/8 & S604/42. Okay for concrete placement at progress areas.
08/05/2026 COT - HCBU - Preslab   Partial Pass 8/4/26: pre-slab at express service shop west half approved
08/07/2026 COT - HCBU - Preslab   Partial Pass 8.7.26
Express building:break room,parts room, and bathroom.
08/20/2026 COT - HCBU - Preslab   Partial Pass 8.20.26
Women's bathroom toilet relocated; men's bathroom sawcuts, hallway sawcut and break room drain connection.
COT - HCBU - Preslab   Scheduled