Permit: TC-COM-0525-01018

Parcel: 11619131A


Addresses:

701 W CONGRESS ST

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Interior Shear Bracing 

Date Description Inspector Results Comments
03/12/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 3/12/26: partial pass for interior shear bracing at GL A-B/1-2
03/27/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 3/26/26:Pre drywall at tubs and dead spaces floors 1-4
04/01/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 4/1/26: fire tape at drywall tub and showers floors 4 and 3
04/09/2026 COT - HCBU - Interior Shear Bracing  Re-inspection required 4-9-26: interior shear inspection-add screws at corridors 6" o.c. along edges & 6" o.c. In the field. Add screws no closer than3/8" from edges/joints and not over penetrate more than 1/32". Schedule st your convenience.
04/15/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 4/15/26: East wing 4th floor 2-layer at ceiling approved ok to proceed, mock up room 420 single layer at east approved.
04/22/2026 COT - HCBU - Interior Shear Bracing  Partial Pass Shower wall 112 dead space, 110 dead space wall south wall. Provide draft stop at 10’. 4/22/2026
04/23/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 4/23/2026 partial pass. 4th floor room 420 drywall nailing approved. Note: remove all drywall screws from rc channel and provide structural screws.
05/15/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 5/15/2026 RC channel at 4th floor corridor both walls approved.
Drywall screws 4th floor units 419,418,417,416,415,414,413,412. Approved.
06/03/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 6/3/2026 Partial pass. RC channel in place at walls and above ceilings north section in rooms 310(not completed),309,308,307,306,305(not completed), 304,303 (missing acres at entry),302 (not completed).

Drywall screw inspection approved in rooms 312,313,314(bathroom ceiling and living area missing screws),315,316,317(not completed),318(not completed),319-320(not completed).
06/04/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 6/4/2026 partial pass. RC channel in place and approved in rooms 220,310,309,308,307,306,305,304,303
Drywall screw approved in room 319.
06/08/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 6/8/2026 partial pass. 3rd floor drywall screw (south half) 312,313,314,315,316,317,318,319,320. Approved. Okay to proceed progress areas.
06/11/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 6/11/2026 partial pass, 4th floor soffits drywall in place 412,413,416,419. Okay to tape and mud.
06/12/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 6/12/2026 partial pass, 4th floor corridor drywall inspection, 3rd floor units north end approved.
06/18/2026 COT - HCBU - Interior Shear Bracing  Partial Pass
06/29/2026 COT - HCBU - Interior Shear Bracing  Not Ready
07/06/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 7/6/2026 1st floor south half drywall screw inspection at all south half units approved.
07/07/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 7/7/2026 Partial pass. 1st floor north half drywall screw inspection 101,102 approved.
07/09/2026 COT - HCBU - Interior Shear Bracing  Partial Pass 7/9/2026 Partial pass. Drywall screw north half units 107,106,105,104,103,102,101. Approved.
2nd floor north half corridor RC channel in place.
3rd floor north half corridor RC channel in place. 3rd floor 1st layer above ceiling in north half corridor.
2nd layer above ceiling north half units 302,303,304,305,306,307,308,309,310
07/10/2026 COT - HCBU - Interior Shear Bracing  Partial Pass Ceiling drywall screw inspection 4th floor. 1st layer ceiling east end stairwell. 3rd floor south end corridor walls approved. 2nd floor south end corridor walls approved. 1st floor south end corridor RC channel approved. North west corridor 1st floor RC channel approved, okay to proceed all progress areas. 7/10/2026
07/13/2026 COT - HCBU - Interior Shear Bracing  Not Ready 7/13/2026not ready. Missing type x throughout. provide specs in wall board that is not type x.
07/15/2026 COT - HCBU - Interior Shear Bracing  Partial Pass Partial pass. East stairwell first layer approved up to third floor landing.
3rd and 4th floor north wing corridor approved.
COT - HCBU - Interior Shear Bracing  Scheduled