Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Interior Shear Bracing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 3/12/26: partial pass for interior shear bracing at GL A-B/1-2 | |
| 03/27/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 3/26/26:Pre drywall at tubs and dead spaces floors 1-4 | |
| 04/01/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/1/26: fire tape at drywall tub and showers floors 4 and 3 | |
| 04/09/2026 | COT - HCBU - Interior Shear Bracing | Re-inspection required | 4-9-26: interior shear inspection-add screws at corridors 6" o.c. along edges & 6" o.c. In the field. Add screws no closer than3/8" from edges/joints and not over penetrate more than 1/32". Schedule st your convenience. | |
| 04/15/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/15/26: East wing 4th floor 2-layer at ceiling approved ok to proceed, mock up room 420 single layer at east approved. | |
| 04/22/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | Shower wall 112 dead space, 110 dead space wall south wall. Provide draft stop at 10’. 4/22/2026 | |
| 04/23/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/23/2026 partial pass. 4th floor room 420 drywall nailing approved. Note: remove all drywall screws from rc channel and provide structural screws. | |
| 05/15/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 5/15/2026 RC channel at 4th floor corridor both walls approved. Drywall screws 4th floor units 419,418,417,416,415,414,413,412. Approved. |
|
| 06/03/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 6/3/2026 Partial pass. RC channel in place at walls and above ceilings north section in rooms 310(not completed),309,308,307,306,305(not completed), 304,303 (missing acres at entry),302 (not completed). Drywall screw inspection approved in rooms 312,313,314(bathroom ceiling and living area missing screws),315,316,317(not completed),318(not completed),319-320(not completed). |
|
| 06/04/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 6/4/2026 partial pass. RC channel in place and approved in rooms 220,310,309,308,307,306,305,304,303 Drywall screw approved in room 319. |
|
| 06/08/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 6/8/2026 partial pass. 3rd floor drywall screw (south half) 312,313,314,315,316,317,318,319,320. Approved. Okay to proceed progress areas. | |
| 06/11/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 6/11/2026 partial pass, 4th floor soffits drywall in place 412,413,416,419. Okay to tape and mud. | |