Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCME - Mechanical Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2026 | COT - HCME - Mechanical Above Ceiling | Not Ready | ||
| 04/15/2026 | COT - HCME - Mechanical Above Ceiling | Not Ready | ||
| 05/04/2026 | COT - HCME - Mechanical Above Ceiling | Partial Pass | 5/4/2026 Mock unit 420 drop lids approved. Okay to proceed progress areas. | |
| 05/18/2026 | COT - HCME - Mechanical Above Ceiling | Re-inspection required | 5/18/26: 2nd and 3rd floor corridors in walls at north building approved. In-wall MEP of 1st floor rooms (101,102,103,104,105,106,107,108,109,110,111,113,114) re-inspection required. Nail plates improperly installed must have (8) 3 -1/2" nails on both sides of 5x18 nail/strap, 5-sided gypsum box required at refrigerator water supply box, seal all penetrations at exterior and interior Fire walls, studs over notched at corridor require fix,properly secure electrical box at bathroom in room 106, room 103 (incomplete framing,plumbing, electrical, mechanical), room 106 (support condensate drain at bathroom) 107 ( leak at bathroom pex), 109 (exterior double studs over notched) 113 (stud at laundry room broken) partial pass for 108 kitchen wall | |
| 05/21/2026 | COT - HCME - Mechanical Above Ceiling | Partial Pass | 5/21/2025 Partial pass. 101,102,103,104,105,106,107,108,109 110,111,112,113,114,117,118,119,120. Approved. All corrections were made. |