Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/10/26: UNIT 420 COURTESY WALKTHROUGH FOR M.E.P approved in wall only | |
| 04/15/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 4/14/26: DWV AND PEX LINES SHALL BE UNDER TEST PRIOR TO CALLING IN INSPECTION | |
| 04/17/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/17/26: ROOM 420 APPROVED FOR MEP, RESILIENT Channel. | |
| 04/22/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4th floor, 3rd floor 2nd floor, 1st floor south corridor rooms DWV on test. 1st floor south corridor were 4” pipe runs through 2x wall causing over notching in various places needs corrections. An inspection will take place on items that need to be fixed. Remove all drywall screws at FHA plates due to non structural screws. Provide nails at each hole per plate. Re inspection required for that also. 4/22/2026 | |
| 04/23/2026 | COT - HCPL - Plumbing Intermediate | Canceled | Canceled per contractor. 4/23/2026 | |
| 04/27/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4th and 3rd south corridor rooms only pex under test. 4/27/2026 | |
| 04/29/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/29/2026 Partial pass. 4th and 3rd floor tubs on test at all south and north corridor rooms. | |
| 05/05/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/5/2026 partial pass. All units. 2nd floor water lines north section of building DWV on test. | |
| 05/14/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/14/2026 Partial pass. 2nd & 3rd floor corridors in walls at west end only approved. Pending north section due to spray foam installation at the time. | |
| 05/18/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 5/18/26: 2nd and 3rd floor corridors in walls at north building approved. In-wall MEP of 1st floor rooms (101,102,103,104,105,106,107,108,109,110,111,113,114) re-inspection required. Nail plates improperly installed must have (8) 3 -1/2" nails on both sides of 5x18 nail/strap, 5-sided gypsum box required at refrigerator water supply box, seal all penetrations at exterior and interior Fire walls, studs over notched at corridor require fix,properly secure electrical box at bathroom in room 106, room 103 (incomplete framing,plumbing, electrical, mechanical), room 106 (support condensate drain at bathroom) 107 ( leak at bathroom pex), 109 (exterior double studs over notched) 113 (stud at laundry room broken) partial pass for 108 kitchen wall | |
| 05/21/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/21/2025 Partial pass. 101,102,103,104,105,106,107,108,109 110,111,112,113,114,117,118,119,120. Approved. All corrections were made. |
|
| 05/22/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/22/2026 partial pass. 1st floor corridors approved. | |
| 12/16/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | 12/16/25: Plumbing underground approved for GL A-C/1.5-3, (pending GL A-B/1-1.5) | |
| 12/18/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Plumbing underground: waste lines and laterals at GL: 2 - North. |