Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 04/12/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
4/10/26: UNIT 420 COURTESY WALKTHROUGH FOR M.E.P approved in wall only |
| 04/15/2026 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
4/14/26: DWV AND PEX LINES SHALL BE UNDER TEST PRIOR TO CALLING IN INSPECTION |
| 04/17/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
4/17/26: ROOM 420 APPROVED FOR MEP, RESILIENT Channel. |
| 04/22/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
4th floor, 3rd floor 2nd floor, 1st floor south corridor rooms DWV on test. 1st floor south corridor were 4” pipe runs through 2x wall causing over notching in various places needs corrections. An inspection will take place on items that need to be fixed. Remove all drywall screws at FHA plates due to non structural screws. Provide nails at each hole per plate. Re inspection required for that also. 4/22/2026 |
| 04/23/2026 |
COT - HCPL - Plumbing Intermediate |
|
Canceled |
Canceled per contractor. 4/23/2026 |
| 04/27/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
4th and 3rd south corridor rooms only pex under test. 4/27/2026 |
| 04/29/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
4/29/2026 Partial pass. 4th and 3rd floor tubs on test at all south and north corridor rooms. |
| 12/16/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
12/16/25: Plumbing underground approved for GL A-C/1.5-3, (pending GL A-B/1-1.5) |
| 12/18/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Plumbing underground: waste lines and laterals at GL: 2 - North. |