Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: TC-COM-0525-01018

Parcel: 11619131A


Addresses:

701 W CONGRESS ST

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
04/12/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/10/26: UNIT 420 COURTESY WALKTHROUGH FOR M.E.P approved in wall only
04/15/2026 COT - HCPL - Plumbing Intermediate  Re-inspection required 4/14/26: DWV AND PEX LINES SHALL BE UNDER TEST PRIOR TO CALLING IN INSPECTION
04/17/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/17/26: ROOM 420 APPROVED FOR MEP, RESILIENT Channel.
04/22/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4th floor, 3rd floor 2nd floor, 1st floor south corridor rooms DWV on test. 1st floor south corridor were 4” pipe runs through 2x wall causing over notching in various places needs corrections. An inspection will take place on items that need to be fixed. Remove all drywall screws at FHA plates due to non structural screws. Provide nails at each hole per plate. Re inspection required for that also. 4/22/2026
04/23/2026 COT - HCPL - Plumbing Intermediate  Canceled Canceled per contractor. 4/23/2026
04/27/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4th and 3rd south corridor rooms only pex under test. 4/27/2026
04/29/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/29/2026 Partial pass. 4th and 3rd floor tubs on test at all south and north corridor rooms.
05/05/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 5/5/2026 partial pass. All units. 2nd floor water lines north section of building DWV on test.
05/14/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 5/14/2026 Partial pass. 2nd & 3rd floor corridors in walls at west end only approved. Pending north section due to spray foam installation at the time.
05/18/2026 COT - HCPL - Plumbing Intermediate  Re-inspection required 5/18/26: 2nd and 3rd floor corridors in walls at north building approved. In-wall MEP of 1st floor rooms (101,102,103,104,105,106,107,108,109,110,111,113,114) re-inspection required. Nail plates improperly installed must have (8) 3 -1/2" nails on both sides of 5x18 nail/strap, 5-sided gypsum box required at refrigerator water supply box, seal all penetrations at exterior and interior Fire walls, studs over notched at corridor require fix,properly secure electrical box at bathroom in room 106, room 103 (incomplete framing,plumbing, electrical, mechanical), room 106 (support condensate drain at bathroom) 107 ( leak at bathroom pex), 109 (exterior double studs over notched) 113 (stud at laundry room broken) partial pass for 108 kitchen wall
05/21/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 5/21/2025 Partial pass. 101,102,103,104,105,106,107,108,109
110,111,112,113,114,117,118,119,120. Approved. All corrections were made.
05/22/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 5/22/2026 partial pass. 1st floor corridors approved.
12/16/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 12/16/25: Plumbing underground approved for GL A-C/1.5-3, (pending GL A-B/1-1.5)
12/18/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Plumbing underground: waste lines and laterals at GL: 2 - North.