Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Firewall/Fire Barrier/Firestop
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 4/1/26: fire tape at drywall tub and showers floors 4 and 3 | |
| 04/02/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Re-inspection required | 4/2/26: Not ready for inspection, multiple rooms have walls that have not been completed, penetrations shall be sealed and all joints must be sealed. Pending 1st and 2nd floor. | |
| 04/08/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 4/8/26: 1st and 2nd fire tape at tubs and shower locations | |
| 04/12/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 4/10/26: Drywall at corridor ceilings and stair 1st layer at drop ceilings | |
| 04/15/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 4/15/26:Drywall 2nd layer on corridor ceilings and at stair walls | |
| 04/23/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 4/23/2026 fire caulking throughout 3rd floor units 4/23/2026 in wall electrical 3rd floor units 320,319,318,317,316,315,314,313,312. Approved. Pending drop ceiling. | |
| 04/24/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Center stair area at exterior. 1st layer of dens shield approved. 4/24/2026 | |
| 04/27/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Center stairs at exterior. 2nd layer of dens shield approved. 4/27/2026 | |
| 05/05/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Partial pass. 2nd floor frame/fire caulk approved in units only. Pending corridors. 5/5/2026 | |
| 05/07/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Canceled | Canceled per contractor. 5/7/2026 | |
| 05/12/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Re-inspection required | 5/12/26: insulation must be completely removed throughout 3rd floor corridors for inspection. Fire blocking required at corridors @ drop ceiling (IBC 718.2.3, 718.2.1.4, 718.2, 718.2.1) please recall inspection once insulation is removed and fire blocking is in place so we can walk 2nd and 3rd floor. All structural nail plates must have drywall screws removed and shall have 8-10d nails on each side (R602.6.1, P2603.2.1). Reinspection required | |
| 05/14/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5/14/2026 Partial pass. 2nd & 3rd floor corridors in walls at west end only approved. Pending north section due to spray foam installation at the time. | |
| 05/18/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Re-inspection required | 5/18/26: 2nd and 3rd floor corridors in walls at north building approved. MEP of 1st floor rooms (101,102,103,104,105,106,107,108,109,110,111,113,114) re-inspection required. Nail plates improperly installed must have (8) 3 -1/2" nails on both sides of 5x18 nail/strap, 5-sided gypsum box required at refrigerator water supply box, seal all penetrations at exterior and interior Fire walls, studs over notched at corridor require fix,properly secure electrical box at bathroom in room 106, room 103 (incomplete framing,plumbing, electrical, mechanical), room 106 (support condensate drain at bathroom) 107 ( leak at bathroom pex), 109 (exterior double studs over notched) 113 (stud at laundry room broken) partial pass for 108 kitchen wall | |
| 05/21/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5/21/2025 Partial pass. 101,102,103,104,105,106,107,108,109 110,111,112,113,114,117,118,119,120. Approved. All corrections were made. |