Inspection Status: Partial Pass
Inspection History: COT - HCBU - Firewall/Fire Barrier/Firestop
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
4/1/26: fire tape at drywall tub and showers floors 4 and 3 |
| 04/02/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Re-inspection required |
4/2/26: Not ready for inspection, multiple rooms have walls that have not been completed, penetrations shall be sealed and all joints must be sealed. Pending 1st and 2nd floor. |
| 04/08/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
4/8/26: 1st and 2nd fire tape at tubs and shower locations |
| 04/12/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
4/10/26: Drywall at corridor ceilings and stair 1st layer at drop ceilings |
| 04/15/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
4/15/26:Drywall 2nd layer on corridor ceilings and at stair walls |
| 04/23/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
4/23/2026 fire caulking throughout 3rd floor units 4/23/2026 in wall electrical 3rd floor units 320,319,318,317,316,315,314,313,312. Approved. Pending drop ceiling. |
| 04/24/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
Center stair area at exterior. 1st layer of dens shield approved. 4/24/2026 |
| 04/27/2026 |
COT - HCBU - Firewall/Fire Barrier/Firestop |
|
Partial Pass |
Center stairs at exterior. 2nd layer of dens shield approved. 4/27/2026 |