Permit: TC-COM-0525-01018

Parcel: 11619131A


Addresses:

701 W CONGRESS ST

Inspection Status: Not Ready

Inspection History: COT - HCME - Mechanical Intermediate

Date Description Inspector Results Comments
04/12/2026 COT - HCME - Mechanical Intermediate Not Ready
04/15/2026 COT - HCME - Mechanical Intermediate Not Ready
04/23/2026 COT - HCME - Mechanical Intermediate Partial Pass Partial pass. Dryer duct in place at units 320,319,318,317,316,315,314,313,312. Pending lines sets along with drop ceiling. 4/23/2026
05/05/2026 COT - HCME - Mechanical Intermediate Partial Pass Partial pass. Dryer ducts in place 2nd floor. 5/5/2026
05/18/2026 COT - HCME - Mechanical Intermediate Re-inspection required 5/18/26: 2nd and 3rd floor corridors in walls at north building approved. In-wall MEP of 1st floor rooms (101,102,103,104,105,106,107,108,109,110,111,113,114) re-inspection required. Nail plates improperly installed must have (8) 3 -1/2" nails on both sides of 5x18 nail/strap, 5-sided gypsum box required at refrigerator water supply box, seal all penetrations at exterior and interior Fire walls, studs over notched at corridor require fix,properly secure electrical box at bathroom in room 106, room 103 (incomplete framing,plumbing, electrical, mechanical), room 106 (support condensate drain at bathroom) 107 ( leak at bathroom pex), 109 (exterior double studs over notched) 113 (stud at laundry room broken) partial pass for 108 kitchen wall
05/21/2026 COT - HCME - Mechanical Intermediate Partial Pass 5/21/2025 Partial pass. 101,102,103,104,105,106,107,108,109
110,111,112,113,114,117,118,119,120. Approved. All corrections were made.
05/22/2026 COT - HCME - Mechanical Intermediate Partial Pass 5/22/2026 partial pass. 1st floor corridors approved.