Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
4/1/26:Please do 4th floor framing above the lid |
| 04/21/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
4/21/2026 partial pass. 1st and 2nd corridor 2nd layer drywall approved. Okay to proceed progress areas. |
| 05/04/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
5/4/2026 Mock unit 420 drop lids approved. Okay to proceed progress areas. |
| 05/12/2026 |
COT - HCBU - Building Above Ceiling |
|
Re-inspection required |
5/12/26: insulation must be completely removed throughout 3rd floor corridors for inspection. Fire blocking required at corridors @ drop ceiling (IBC 718.2.3, 718.2.1.4, 718.2, 718.2.1) please recall inspection once insulation is removed and fire blocking is in place so we can walk 2nd and 3rd floor. All structural nail plates must have drywall screws removed and shall have 8-10d nails on each side (R602.6.1, P2603.2.1). Reinspection required |