| 04/30/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Verified 2nd and third floor interior hold downs at interior shear walls. 4/30/2026 |
| 05/13/2026 |
COT - HCBU - Interior Shear Bracing |
|
Canceled |
Canceled per contractor. 5/13/2026 |
| 05/18/2026 |
COT - HCBU - Interior Shear Bracing |
|
Re-inspection required |
5/18/26: fasteners at sheathing must be no closer than 3/8" from edge and shall not penetrate more than 1/8", anchor bolts and shot pins must be spaced per approved plans (over spaced throughout), anchor bolts required 12" from edge of sill plate, hold downs verified in correct locations in rooms (123,124,125,126) |
| 05/22/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
5/22/2026 pins and titans have been corrected throughout the first floors in all units. Okay to proceed progress areas. |
| 06/05/2026 |
COT - HCBU - Interior Shear Bracing |
|
Re-inspection required |
6/5/2026 3rd floor interior shear wall needs to be re walked at marked areas. Double check bottom plate attachments to deck. |
| 06/08/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
6/8/2026 3rd floor interior shear approved. |
| 06/10/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
6/10/2026 2nd floor interior sheathing approved. |
| 06/12/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
6/12/2027 1st floor interior shear osb approved. |
| 06/29/2026 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
|
| 07/01/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
RC channel 3rd floor units 326, 325, 324, 323,322,321,320,319,318,317, 316,315,314,313,312,311,310,309,307,306,305,304,303,302,301,308. 7/1/2026 |
| 07/10/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
RC Channel 2nd floor in place in all units north half and west end up to unit 220. Pending 2nd half heading south on west end. 7/10/2026 |
| 07/13/2026 |
COT - HCBU - Interior Shear Bracing |
|
Not Ready |
7/13/2026 last 5 units RC 2nd floor not ready. Missing screws at marked areas throughout. |
| 07/14/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
|
| 07/20/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
7-20-26: RC at 1st, 2nd, & 3rd floor corridors inspected & approved. Okay to cover progress areas. |
| 07/21/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
7/21/26: partial pass for Dens Glass screw pattern for balcony ceilings, Exterior Sheathing at south end of building floors 1-3 approved. |