| 08/13/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
|
| 08/20/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Not Ready |
8/20/2026 3rd floor drop ceilings inspection units 308,305(fire caulk low voltage lines and patch hole in bathroom. Seal sprinkler line in closet) 304( seal hole at Smurf tub) stopped inspections. |
| 08/21/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
8/21/2026 Partial pass 3rd floor units. 308,305,304,301,310,314,320,323,326 |
| 08/28/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Re-inspection required |
8-28-26: 2nd floor above ceiling MEP's at room's 201-add a support at bathroom exhaust, 202-provide exhaust supports at soffit areas at 4' intervals; within 2' of a 90 degree and at exhaust joints to prevent bowing. Also, add a strap above ceiling for bathroom exhaust. Reschedule inspections after corrections are made in all rooms |
| 08/31/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Re-inspection required |
8-31-26:mechanical above ceiling at room’s 201, 202, 203, 204-years to flex, 205-strap flex, 206-strap exhaust/strap to restroom fan exhaust, 207, 208-leak at restroom exhaust/support flex in restroom off grid, tear on flex in restroom, 209-supports at 4' intervals to exhausts, 210-tear on flex living room, support to exhaust at bedroom closet-at 90 degree elbow/tear on flex at restroom/connect restroom fan, support to 6" exhaust in other bedroom, 211- supports to exhaust at 4' intervals,. 212-supports to exhausts at 4' intervals. Stopped inspection-additional items may be noted. |
| 09/03/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
Dropped ceilings in Level Two units, and Level Three corridors. |
| 09/10/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
9/10/26 inspection called for above ceiling truss cavity for fire stop tape first floor and second floor corridor/North corridor lighting has electrical wire that needs to be supported properly needs a nail stop on a line set and identify and frameing in the area at stairs in the north east corridor, where a soffit is required to accommodate ductwork, please frame that in prior to reinspection. |
| 09/15/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
2nd floor corridors. From unit 226. Pending center area near center stairwell. North corridor 2nd floor up to 2 units before north stairwell area Approved. Okay to proceed progress areas. 9/15/2026 |
| 09/16/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
|
| 09/23/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
9/23/2026 Partial pass. MEP approved at dropped ceilings. 1st floor. Units 111-126. (125) not ready. Okay to proceed progress areas. |
| 09/25/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Re-inspection required |
Provide approved plans and assembly instructions if applicable. |
| 09/28/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
9/28/2026 Partial pass. 1st floor MEP at dropped ceilings units 109,107,106,103,104,105(closet space ceiling needs to be corrected),108(fire caulking required behind p trap). |
| 10/07/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Not Ready |
|
| 10/09/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
|
|
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
10/12/26: mechanical at 2nd floor corridor soffit above ceiling together with dropped ceiling framing at room 125 approved. |