Permit: TC-COM-0525-01016

Parcel: 116206340


Addresses:

115 S LINDA AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
01/16/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 1/16/26: plumbing underground approved from GL A-C/1-3 (ok to backfill progress area, shading required)
06/03/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 6/3/2026 partial pass. 2nd & 3rd floors pex under test. Okay to insulate hot water lines. Still need to verify straps, plates, and fire caulking at intermediate.
06/08/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 6/8/2026 partial pass. 3rd floor MEP approved. Both west and north end units. Okay to proceed progress areas.
06/10/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 6/10/2026 partial pass. DWV 1st - 3rd floors approved. Pending tub test.
06/15/2026 COT - HCPL - Plumbing Intermediate  Re-inspection required 6-15-26: framing, MEP's at room's 201- draft stop missing, missing nails at strap at entryway east wall, add 12 nails to each side of top plate splice, DWV at washer/dryer, seal penetrations at above ceiling decking along east wall , properly feed feeders through top plate at east wall and seal penetrations at top plate.decking, add plastic bushing at sub panel feeder, add nails to hold down at entryway /east wall, 202- missing deft stop, fire caulk penetrations at above ceiling decking, seal top plate penetrations at marked location, seal hvac line set penetration at above ceiling decking, missing strap at shear wall & nail strap to backing behind tub, add strap to DWV at laundry room, 203-missing draft stop, add strap to DWV at laundry, 12 nails at each side of top splices, secure pex lines within 12", ground pancake box, add plastic bushing at subpanel feeder. Stopped inspection-additional items may added.
06/18/2026 COT - HCPL - Plumbing Intermediate  Partial Pass
06/25/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 6.25.26
1st floor south wing.
06/26/2026 COT - HCPL - Plumbing Intermediate  Partial Pass
COT - HCPL - Plumbing Intermediate  Requested