Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2026 | COT - HCME - Mechanical Intermediate | Partial Pass | 6/8/2026 partial pass. 3rd floor MEP approved. Both west and north end units. Okay to proceed progress areas. | |
| 06/15/2026 | COT - HCME - Mechanical Intermediate | Re-inspection required | 6-15-26: framing, MEP's at room's 201- draft stop missing, missing nails at strap at entryway east wall, add 12 nails to each side of top plate splice, DWV at washer/dryer, seal penetrations at above ceiling decking along east wall , properly feed feeders through top plate at east wall and seal penetrations at top plate.decking, add plastic bushing at sub panel feeder, add nails to hold down at entryway /east wall, 202- missing deft stop, fire caulk penetrations at above ceiling decking, seal top plate penetrations at marked location, seal hvac line set penetration at above ceiling decking, missing strap at shear wall & nail strap to backing behind tub, add strap to DWV at laundry room, 203-missing draft stop, add strap to DWV at laundry, 12 nails at each side of top splices, secure pex lines within 12", ground pancake box, add plastic bushing at subpanel feeder. Stopped inspection-additional items may added. | |
| 06/18/2026 | COT - HCME - Mechanical Intermediate | Not Ready | 6.18.26 HVAC refrigerant lines running A2L Freon will need to be in a shaft. |
|
| 06/25/2026 | COT - HCME - Mechanical Intermediate | Partial Pass | 6.25.26 1st floor south wing. |
|
| 06/26/2026 | COT - HCME - Mechanical Intermediate | Partial Pass | ||
| COT - HCME - Mechanical Intermediate | Requested |