Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/20/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | Partial pass. 1st floor corridor SD screws and hangers. Pending 20’ south west end. Missing SD screws. 4/20/2026 | |
| 04/27/2026 | COT - HCBU - Building Above Ceiling | Canceled | Canceled per contractor. 4/27/2026 | |
| 04/29/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 4/29/2026 Partial pass. 3rd floor corridors West and North approved above ceiling. Okay to proceed with netting and blown in insulation. | |
| 05/20/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/20/2026 partial pass. 1st floor corridor ceiling 1st layer drywall approved. Okay to proceed progress areas. | |
| 06/29/2026 | COT - HCBU - Building Above Ceiling | Not Ready | ||
| 08/13/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | ||
| 08/20/2026 | COT - HCBU - Building Above Ceiling | Not Ready | 8/20/2026 3rd floor drop ceilings inspection units 308,305(fire caulk low voltage lines and patch hole in bathroom. Seal sprinkler line in closet) 304( seal hole at Smurf tub) stopped inspections. | |
| 08/21/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 8/21/2026 Partial pass 3rd floor units. 308,305,304,301,310,314,320,323,326 | |
| 08/28/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 8-28-26: drywall screw inspection above ceiling only at south stair case approved for tape & texture. | |
| 09/03/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | Dropped ceilings in Level Two units. | |
| 09/10/2026 | COT - HCBU - Building Above Ceiling | Not Ready | ||
| 09/15/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 2nd floor corridors. From unit 226. Pending center area near center stairwell. North corridor 2nd floor up to 2 units before north stairwell area Approved. Okay to proceed progress areas. 9/15/2026 | |
| 09/16/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | ||
| 09/23/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 9/23/2026 Partial pass. MEP approved at dropped ceilings. 1st floor. Units 111-126. (125) not ready. Okay to proceed progress areas. | |
| 09/25/2026 | COT - HCBU - Building Above Ceiling | Re-inspection required | Provide approved plans and assembly instructions if applicable. | |
| 09/28/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 9/28/2026 Partial pass. 1st floor MEP at dropped ceilings units 109,107,106,103,104,105(closet space ceiling needs to be corrected),108(fire caulking required behind p trap). | |
| 10/07/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | ||
| 10/09/2026 | COT - HCBU - Building Above Ceiling | Re-inspection required | 10.9.26 Insulate hot water line at 2nd floor corridor |
|
| 10/12/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 10/12/26: MEP's at 2nd floor corridor soffit above ceiling together with dropped ceiling framing at room 125 approved. Okay to continue with construction at progress areas. |