Inspection Status: Not Ready

Inspection History: COT - LCEL - Electrical Intermediate

Date Description Inspector Results Comments
08/13/2024 COT - LCEL - Electrical Intermediate Not Ready 8/13/24: needed underground inspection
08/15/2024 COT - LCEL - Electrical Intermediate Partial Pass 8/13/24: needed underground inspection
8/15/24: electrical rough-in per plans at perimeter walls ok to proceed.
08/23/2024 COT - LCEL - Electrical Intermediate Partial Pass 8/23/2024. The rest of electrical rough in is in place okay to proceed with drywall. Leave open plumbing walls prior to inspection.
08/29/2024 COT - LCEL - Electrical Intermediate Partial Pass 8/13/24: needed underground inspection
8/15/24: electrical rough-in per plans at perimeter walls ok to proceed.

8/23/2024. The rest of electrical rough in is in place okay to proceed with drywall. Leave open plumbing walls prior to inspection.
8/29/24: electrical rough in complete ok to proceed. Hard lid areas passed ok to proceed
09/16/2024 COT - LCEL - Electrical Intermediate Passed