Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/15/2025 |
COT - HCBU - Building Progress |
|
Passed |
Canopy over main entry area. |
| 05/30/2024 |
COT - HCBU - Building Progress |
|
Partial Pass |
Footings |
|
COT - HCBU - Building Progress |
|
Re-inspection required |
7/29/24: pre slab not ready need 3rd party inspection for epoxy dowels |
| 07/31/2024 |
COT - HCBU - Building Progress |
|
Canceled |
Contractor cancelled. |
| 08/01/2024 |
COT - HCBU - Building Progress |
|
Partial Pass |
Rebar placement for oven areas and washer area. Dowels are in place: OK to place concrete in progress areas. |
| 08/19/2024 |
COT - HCBU - Building Progress |
|
Partial Pass |
South wall at main oven area: sheet rock covered walls (one side), in wall plumbing for suppression system under hydro test at 100 psi. |