Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Underground electric conduits for future solar structures: 2 each 2” conduits, 1 each 1 1/2” conduit, 4 each 1” conduits. OK to cover progress areas. |
| 04/21/2025 |
COT - HCEL - Electrical Progress |
|
Passed |
|
| 06/13/2024 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Conduits for cafe service area. Inspection performed on 12 June 2024. |
| 07/15/2024 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Electric underground at conduits (3” - 1”) from new panel areas to proposed transformer area. Ok to cover and include safety tape in progress areas. |
| 10/02/2024 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Primary electric,conduits; 10 each 4” conduits to transformer area. Ok to cover progress areas. |
| 10/17/2024 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
New disconnect for interior power. Power kill at 0900 17 October.. Called in to TEP to be energized on 18 October (Ruben). Code INCR. |