Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
11/15/2023 COT - HCBU - Framing Partial Pass Wall and ceiling framing is complete. Okay to install sheet rock on ceiling and one side interior walls.
12/01/2023 COT - HCBU - Framing Partial Pass Partial pending framing at duct entry from ceiling. Looked at drywall 5/8 type X nailing pattern in scanner room #105. Okay for lead line at joints and screws. 12/1/2023
12/06/2023 COT - HCBU - Framing Partial Pass 12/6/23 firsts layer in duct shaft complete on 3 walls, north wall not complete, lead sheeting complete in X-ray room
12/12/2023 COT - HCBU - Framing Not Ready Not ready. 12/12/2023
12/13/2023 COT - HCBU - Framing Partial Pass Partial pass. Scanner room. Completed framing at duct coming in end wall. Above ceiling grids approved okay for hard lid. 12/13/2023
12/20/2023 COT - HCBU - Framing Partial Pass Ceiling grids for pre scan #103, work #104, control room #106. 12/20/2023
COT - HCBU - Framing Passed