Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 11/15/2023 |
COT - HCBU - Framing |
|
Partial Pass |
Wall and ceiling framing is complete. Okay to install sheet rock on ceiling and one side interior walls. |
| 12/01/2023 |
COT - HCBU - Framing |
|
Partial Pass |
Partial pending framing at duct entry from ceiling. Looked at drywall 5/8 type X nailing pattern in scanner room #105. Okay for lead line at joints and screws. 12/1/2023 |
| 12/06/2023 |
COT - HCBU - Framing |
|
Partial Pass |
12/6/23 firsts layer in duct shaft complete on 3 walls, north wall not complete, lead sheeting complete in X-ray room |
| 12/12/2023 |
COT - HCBU - Framing |
|
Not Ready |
Not ready. 12/12/2023 |
| 12/13/2023 |
COT - HCBU - Framing |
|
Partial Pass |
Partial pass. Scanner room. Completed framing at duct coming in end wall. Above ceiling grids approved okay for hard lid. 12/13/2023 |
| 12/20/2023 |
COT - HCBU - Framing |
|
Partial Pass |
Ceiling grids for pre scan #103, work #104, control room #106. 12/20/2023 |
|
COT - HCBU - Framing |
|
Passed |
|