Inspection Status: Canceled
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 07/17/2026 |
COT - HCBU - Preslab |
|
Canceled |
7-17-26: canceled by contractor. |
| 07/21/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
7-21-26: pre slab, excavation/reinforcement on exterior footers only from G/L: A-L/ 6-10 verified per footing schedule and keynotes located on S1.1. Okay for concrete placement at progress areas. |
| 07/22/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
7/22/26: exterior footings only from GL: A-L/ 1-6 verified per approved plans and meet 3'' clearance from earth. Okay for concrete placement at progress areas. |
| 08/04/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
8/4/2026 Partial pass. Elevator sump pit approved. Okay for concrete placement. |
| 09/01/2026 |
COT - HCBU - Preslab |
|
Re-inspection required |
9/1/26: not inspected due to non-compacted soil throughout foundation (wet soil conditions) Soil must be compacted around conduits, remove debris such as blocks & rebar not attached to reinforcement. Reschedule this inspection when dry. |
| 09/02/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
|
| 09/10/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
9/10/26: reinforcement for CMU wall at line 10 together with reinforcement at line L approved to grout 1st lift. |