Inspection Status: Canceled
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 07/17/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Canceled |
7-17-26: canceled by contractor. |
| 07/21/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
7-21-26: excavation/reinforcement on exterior footers only from G/L: A-L/ 6-10 verified per footing schedule and keynotes located on S1.1. Okay for concrete placement at progress areas. |
| 07/22/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
7/22/26: exterior footings only from GL: A-L/ 1-6 verified per approved plans and meet 3'' clearance from earth. Okay for concrete placement at progress areas. |
| 07/24/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
7-24-26: interior column footings at G/L: 7, 9, 10 verified per S1.1/Footing schedule F15, F12, F14, F8, F10 & Column Schedule C1, C2, C4, C1, C3. Okay for concrete placement. |
| 08/03/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8-3-26: partial pass for excavation/reinforcement at equipment room step footing & elevator pit( verified verticals for 8 " walls and #5's @12" o.c. each way At elevator pit) Reinforcement verified S2.1/14 & S.2.1/16-Contractor will reschedule reinforcement for sump pit at elevator at a later date. Okay for concrete placement at progress areas. Please submit sump pit detail to the city for review/approval. |
| 08/04/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8/4/2026 Partial pass. Elevator sump pit approved. Okay for concrete placement. |
| 08/07/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8-7-26: reinforcement at elevator pit walls verified per S2.1 Detail 14. Okay for concrete placement. |
| 08/13/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Not Ready |
8/13/2026 12 spread footings on the north side. Includes F11, F12, F13, F14 footings not ready. Remove loose fill and provide the minimum of 3" from earth. If dirt on rebar has to be cleaned. |
| 08/14/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8/14/2026 Partial pass. Corrections have been made. 11 spread footings on the north side. Includes F11, F12, F13, F14 footings as seen on S1.1. Approved. Okay for concrete placement. |
| 08/18/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8-18-26: reinforcement/excavation for a spread footing located along the southeast quad of site verified per S1.1/F11. Okay for concrete placement. |
| 08/25/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
8-25-26: reinforcement at elevator shaft approved for 4th lift at 18' 4". |