Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
08/19/2026 COT - HCBU - Masonry Pregrout  Partial Pass 8-19-26: reinforcement at elevator hoist way verified per plans- okay to grout 1st. lift at 4' 8".
08/21/2026 COT - HCBU - Masonry Pregrout  Partial Pass 8-21-26: reinforcement at elevator hoist way verified per plans. Okay to grout 2nd lift at 9' 4".
08/24/2026 COT - HCBU - Masonry Pregrout  Partial Pass 8/24/2026 Building #3. 3rd lift at mechanical room/elevator shaft. 9'4-14'. Approved per 3rd party report.
COT - HCBU - Masonry Pregrout  Scheduled