Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCPL - Plumbing Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/27/2026 | COT - HCPL - Plumbing Progress | Passed | 4-27-26: approved. | |
| 11/17/2025 | COT - HCPL - Plumbing Progress | Partial Pass | 11-17-25: underground plumbing verified per plans. Okay to backfill-shading required. Note: schedule a dowel & vapor barrier inspection prior to pour back. |
|
| 12/23/2025 | COT - HCPL - Plumbing Progress | Partial Pass | 12-23-25: in wall domestic needs to be under test. Okay to drywall warehouse side but reschedule domestic test prior to covering other side. |