Inspection Status: Partial Pass
Inspection History: COT - LCEL - Grounding/BondingĀ
| Date |
Description |
Inspector |
Results |
Comments |
| 01/06/2026 |
COT - LCEL - Grounding/BondingĀ |
|
Partial Pass |
1-6-26: 5 light pole cages inspected -Verified Schedule 40 conduit with proper bonding at each. |
| 03/03/2026 |
COT - LCEL - Grounding/BondingĀ |
|
Partial Pass |
3-3-26: verified splash pad equipotential bonding & bonding to structures. Okay for concrete placement at progress areas. |