Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCPL - Sewer
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2026 | COT - LCPL - Sewer | Partial Pass | 1-9-26: approximately 120' of SDR35-6" PVC sewer line installed. Okay to backfill trench with shading materials. | |
| 01/12/2026 | COT - LCPL - Sewer | Partial Pass | 1-12-26: approximately 150' of SDR35-6" PVC sewer line installed. Okay to backfill trench with shading materials. | |
| 01/23/2026 | COT - LCPL - Sewer | Partial Pass | Total of 650’ SDR35 of HCS. Test gauge at man hole. Approved. Pending tie into buildings. 1/23/2026 | |
| 01/27/2026 | COT - LCPL - Sewer | Partial Pass | 1-27-26: verified 5 locations of sewer tie in throughout site. 4 located on west side of Building 1 & 2,and the 5th at north side of Building 3. Okay to backfill using shading materials. | |
| 07/08/2026 | COT - LCPL - Sewer | Passed | ||
| 12/04/2025 | COT - LCPL - Sewer | Partial Pass | 12-4-25: verified trench depth at 6' plus with a 6" SDR35 PVC pipe and tracer wire. Okay to backfill approximately 50' of trench using shading materials. Note: partial pass pending air test on sewer line. |
|
| 12/05/2025 | COT - LCPL - Sewer | Canceled | 12-5-25: canceled by contractor. | |
| 12/09/2025 | COT - LCPL - Sewer | Canceled | 12-9-25: canceled by contractor. | |
| 12/11/2025 | COT - LCPL - Sewer | Partial Pass | 12-11-25: verified trench depth on a 6" SFR35 PVC sewer line. Okay to backfill approximately 40' of trench using shading materials. | |
| 12/12/2025 | COT - LCPL - Sewer | Canceled | 12/12/2025 canceled per contractor. | |
| 12/16/2025 | COT - LCPL - Sewer | Partial Pass | 12-16-25: 160' of 6" SDR35 PVC sewer line installed-okay to backfill progress areas. | |
| 12/18/2025 | COT - LCPL - Sewer | Partial Pass | 12-18-25: approximately 80' of 6" SDR35 PVC sewer line installed-okay to backfill progress areas using shading materials. |