Inspection Status: Partial Pass
Inspection History: COT - LCME - Mechanical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 04/24/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
4-24-26: partial pass for mechanical at Buildings 1 & 2 ( pending pressure test). Okay to continue with construction at progress areas. |
| 05/01/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
5-1-26: verified framing with cassettes in place, proper supports for refrigerant lines & installation of condensate lines at Building 1 & 2. Okay to continue construction at progress areas. |
| 05/18/2026 |
COT - LCME - Mechanical Intermediate |
|
Partial Pass |
5/18/2026 Partial pass. Admin building above ceiling for mechanical approved. |