Permit: TC-COM-0424-00665

Parcel: 13801001D


Addresses:

6100 S 12TH AV

Inspection Status: Partial Pass

Inspection History: COT - LCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
03/13/2026 COT - LCPL - Plumbing Intermediate  Partial Pass 3-13-26: verified DWV for Building 1 under test.
03/31/2026 COT - LCPL - Plumbing Intermediate  Partial Pass 3-31-26: domestic copper lines at restrooms for building's 1 & 2 verified under test. Okay to continue with construction at progress areas.
04/24/2026 COT - LCPL - Plumbing Intermediate  Partial Pass 4-24-26: above ceiling/in wall plumbing for Buildings 1 & 2 approved. Okay to continue with construction at progress areas.
09/22/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 9-22-25: underground plumbing for breakroom, janitorial & family room verified under test & per plan. Okay to backfill progress areas
09/30/2025 COT - LCPL - Plumbing Intermediate  Re-inspection required 9-30-25: DWV going through CMU walls must be sleeved (2 pipe diameters).See concrete structural notes #4 for details.
10/02/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 10-2-25: underground plumbing on building 2 verified per plans & under test . Okay to backfill.
10/06/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 10-6-25: underground main swimming pool floor plumbing verified under test and per plans. Okay to backfill progress areas.
10/28/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 10/28/25
Ok to proceed in progress areas.
11/03/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 11-3-25: in wall DWV & domestic for men's restroom in Building 2 verified under test. Domestic verified at 100 psi on all gauges. Okay to continue with construction at progress areas.
11/21/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 11-21-25: underground plumbing for splash pad verified under test at 35psi and layout per plans. Bonding in place pending rebar bonding. Okay to backfill progress areas using shading materials.
12/18/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 12-18-25: underground plumbing at Building 3- pool equipment room verified under test. An RFI to the city has been submitted showing new location of vents. Okay to backfill at own risk pending city approval.