Inspection Status: Partial Pass
Inspection History: zzzPDSD Building Division - Site Excavation/Layout/Rebar
| Date |
Description |
Inspector |
Results |
Comments |
| 09/22/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Partial Pass |
9-22-25: reinforcement for building 2 of the aquatic center verified per details, F1/C2, F2/C1, & non bearing partition walls 2/S3.2. Okay for concrete placement at progress areas. |
| 09/29/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Partial Pass |
9-29-25: reinforcement on Building 2's stem wall verified per plans-okay to grout at 16". |
| 10/02/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Partial Pass |
10-2-25: reinforcement for 10 footings/columns between Gridline 7-8 verified per S1.1 Detail F2 & S3.2 Detail 4. Okay for concrete placement at progress areas. |
| 10/14/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Partial Pass |
10-14-25: reinforcement for slab on grade on Building 2 verified per S1.1 keynote #1. Okay for concrete placement at progress area. |
| 10/15/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Partial Pass |
10-15-25: reinforcement for CMU wall at Gridline 3.5-5.5 on Building 1 verified per approved plans-Okay to grout 1st lift at 4'. |
| 10/30/2025 |
zzzPDSD Building Division - Site Excavation/Layout/Rebar |
|
Passed |
10/30/25 Partial pass for plumbing and rebar at both pools pending splashpad, ok to backfill, shockcrete pools. Both structures ok to proceed to next lift, reinforcement verified |