Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Above Ceiling

Date Description Inspector Results Comments
01/03/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.

11/6/23: D0300 Above ceiling complete.

11/22/23: B0300 main room above ceiling complete. Pending small rooms.

12/5/23: Above ceiling complete in B0300, Complete in A0300, Above ceiling in main corridor Area H and Area G from grid line E. Ok to proceed in progress areas.
12/14/23: Mechanical above ceiling in F0200 and K0400 passed ok to place grid tiles in progress areas.
1/3/23: above ceiling complete in corridor area J, B0305 vestibule, C0300 Vestibule, D0200 corridor, K0200 corridor, J0321 hallway, F0300 vestibule.
02/22/2024 COT - HCME - Mechanical Above Ceiling Passed
07/19/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200
08/15/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs
10/04/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed
10/11/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed
10/20/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.
10/26/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.
11/06/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.

11/6/23: D0300 Above ceiling complete.
11/22/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.

11/6/23: D0300 Above ceiling complete.

11/22/23: B0300 main room above ceiling complete. Pending small rooms.
12/05/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.

11/6/23: D0300 Above ceiling complete.

11/22/23: B0300 main room above ceiling complete. Pending small rooms.

12/5/23: Above ceiling complete in B0300, Complete in A0300, Above ceiling in main corridor Area H and Area G from grid line E. Ok to proceed in progress areas.
12/14/2023 COT - HCME - Mechanical Above Ceiling Partial Pass 7/18/23. Hard duct, room L0200

8/15/23: J0321 hard duct above room ready to connect to VAV and insulate, K0200 break room area run offs from VAV complete, L0310 VAV 1-5 complete in room and run offs

10/4/23: Mechanical Above ceiling in L0300 and L0200 per plan ok to proceed

10/11/23: K Block mechanical above ceiling ok to proceed

10/20/23: G0300 Main area above ceiling passed.

10/26/23: D0205 I.T and small rooms in G0300 Mechanical above ceiling passed.

11/6/23: D0300 Above ceiling complete.

11/22/23: B0300 main room above ceiling complete. Pending small rooms.

12/5/23: Above ceiling complete in B0300, Complete in A0300, Above ceiling in main corridor Area H and Area G from grid line E. Ok to proceed in progress areas.
12/14/23: Mechanical above ceiling in F0200 and K0400 passed ok to place grid tiles in progress areas.