Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCME - Mechanical Intermediate
Permit Number - TC-COM-0423-01131
Inspection Description - COT - HCME - Mechanical Intermediate
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/22/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
02/22/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
02/22/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
07/19/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready | |
07/26/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 |
|
08/02/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct |
|
08/07/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 |
|
08/18/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete |
|
08/21/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. |
|
08/23/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. |
|
08/25/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct |
|
08/29/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. |
|
08/31/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. |
|
09/06/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. |
|
09/12/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate |
|
09/14/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. |
|
09/18/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. |
|
09/20/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. |
|
09/22/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 |
|
09/28/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. |
|
10/02/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. |
|
10/04/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 7/18/23. Not ready 7/24/23: From column M3 to west side corridor, Hard duct in area G4 (VAV 1-27) 7/26/23: From column M3 to L3, Hard duct in corridor K0400 8/2/23: K0200 Hard duct 8/7/23: VAV 1 West side corridor M0300 8/18/23: L0300 All VAV under air test, Hard duct in L0300 run offs complete 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. |
|
10/09/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. |
|
10/11/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. |
|
10/12/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 10/12/23: main corridor hard duct 76"x36" from column B to A ok to insulate. | |
10/18/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/18/23:D0300 vestibule 76"x36" hard duct ok to insulate, D0300 all room run offs complete ok to insulate, B0300 main supply duct, B0315 duct from VAV to supply, VAV 3-14 into room. |
|
10/20/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/21/23: K0200 break room hard duct passed, east corridor to K column hard duct passed. 8/23/23: K0200 3 transfers on north wall, supply Hard duct column k to j3, L0200 VAV 29 complete, G0300 hard duct transition from west to north. 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/20/23: B0300 VAV 3-12 hard duct complete, A0300 main duct work in main area sealed and supported. Ok to proceed |
|
10/24/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | ||
10/26/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/18/23:D0300 vestibule 76"x36" hard duct ok to insulate, D0300 all room run offs complete ok to insulate, B0300 main supply duct, B0315 duct from VAV to supply, VAV 3-14 into room. 10/26/23: A0300 hard duct ok to insulate |
|
11/01/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/18/23:D0300 vestibule 76"x36" hard duct ok to insulate, D0300 all room run offs complete ok to insulate, B0300 main supply duct, B0315 duct from VAV to supply, VAV 3-14 into room. 10/26/23: A0300 hard duct ok to insulate 11/1/23: 18"X24" VAV 3-8 hard duct from column E to column B3 ok to proceed. |
|
11/06/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/25/22: Corridor K hard duct 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/20/23: B0300 VAV 3-12 hard duct complete, A0300 main duct work in main area sealed and supported. Ok to proceed 11/6/23: A0300 return from vestibule into A0300, 18"x24" hard duct from column B3 to A3 ok to insulate. |
|
11/09/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 10/12/23: main corridor hard duct 76"x36" from column B to A ok to insulate. 11/9/23: supply hard duct to VAV 3-18 from main to vestibule on east side. |
|
11/14/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/20/23: B0300 VAV 3-12 hard duct complete, A0300 main duct work in main area sealed and supported. Ok to proceed 11/6/23: A0300 return from vestibule into A0300, 18"x24" hard duct from column B3 to A3 ok to insulate. 11/14/23: condensate line for mini split in D0300, East side corridor VAV 3-18 (2) spiral duct run offs on south end ok to insulate, Backdraft damper in East bathrooms installed, K corridor spiral duct run offs from VAV 1-15, VAV 1-8 AND VAV 1-9 completed ok to insulate. |
|
11/17/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 8/29/23: J0330 corridor Hard duct (18x24) from column M-N ok to insulate, Hard Duct supply from column K to H3 ok to insulate. 8/31/23: G0300 hard duct at VAV 1-14 and 1-13 ready to insulate, VAV 1-12 tied into main, J0215 duct run offs complete, main hard duct from column H3-H ok to insulate, L0300 small rooms return and run offs complete and insulated. 9/6/23: D0200 Hard duct ok to insulate, Run-offs over J0321 ok to insulate, K corridor round tie to VAV 1-12, transition from hard duct to VAV 1-13 in G0300, VAV 3-3 in G0300 passed. 9/12/23: Hard duct supply 18"x24" Column K-H, Main duct tie into L0300 ok to insulate 9/14/23: main corridor hard duct to column F3 ok to insulate after pressure test, all run offs in G0300 main area complete, All run offs to rooms in G0300 complete. 9/18/23: Hard duct in G0315 complete, G0300 main room runoffs complete, L0205 L0210 L0215 return air registers complete, G0300 vestibule tie into main duct in corridor. 9/20/23: Hard duct 76"x36" tie into K0200, Hard duct 76"x36" tie into VAV 1-26, G0300 main duct run-off complete to VAV 1-17 ok to insulate. 9/22/23: G0300 VAV 1-20 run off complete, FC-11 hard duct into K0300 9/28/23: D0300 Main supply hard duct per plan. 10/2/23:D0300 main duct supply tie into VAV 3-7, 18"x24" hard duct in main corridor from column F3 to H ok to insulate. 10/4/23: 18"x24" hard duct in main corridor from column H to E ok to insulate. 10/9/23: Hard duct 76"x36" from column E to A ok to insulate, D0300 hard duct complete with all VAV tied in. 10/18/23:D0300 vestibule 76"x36" hard duct ok to insulate, D0300 all room run offs complete ok to insulate, B0300 main supply duct, B0315 duct from VAV to supply, VAV 3-14 into room. 10/26/23: A0300 hard duct ok to insulate 11/1/23: 18"X24" VAV 3-8 hard duct from column E to column B3 ok to proceed. 11/17/23: D0300 small rooms mechanical above ceiling passed. |
|
12/05/2023 | COT - HCME - Mechanical Intermediate | Partial Pass | 10/12/23: main corridor hard duct 76"x36" from column B to A ok to insulate. 11/9/23: supply hard duct to VAV 3-18 from main to vestibule on east side. 12/5/23: F0200 corridor hard duct from VAV 3-19 ok to insulate. |