Inspection Status: Passed

Inspection History: COT - HCME - Hydronic Piping 

Permit Number - TC-COM-0423-01131

Inspection Description - COT - HCME - Hydronic Piping 

Inspection Status - Passed

Date Description Inspector Results Comments
02/22/2024 COT - HCME - Hydronic Piping  Passed
02/22/2024 COT - HCME - Hydronic Piping  Passed
07/16/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200
07/19/2023 COT - HCME - Hydronic Piping  Partial Pass 7/13/23. Corridor K400
08/02/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
07/26/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
08/02/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
08/21/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return

8/21/23: L0300 all VAV hydro tested
08/25/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
8/25/23: not ready
08/29/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
8/25/23: not ready
8/29/23: hydronic piping under air test from L0200 to K0200 (VAV 1-21, 1-22, 1-29, 1-30, 1-25)
09/20/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return

8/21/23: L0300 all VAV hydro tested

9/20/23: hydronic piping under air test from main entrance to D0300 run offs ok to insulate
10/04/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
8/25/23: not ready
8/29/23: hydronic piping under air test from L0200 to K0200 (VAV 1-21, 1-22, 1-29, 1-30, 1-25)
10/4/23: Hydronic piping under air test to VAV 1-10
10/20/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return

8/21/23: L0300 all VAV hydro tested

9/20/23: hydronic piping under air test from main entrance to D0300 run offs ok to insulate
10/20/23: hydronic piping under pressure from main entrance to D0300 feeding all VAV's
10/30/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
8/25/23: not ready
8/29/23: hydronic piping under air test from L0200 to K0200 (VAV 1-21, 1-22, 1-29, 1-30, 1-25)
10/4/23: Hydronic piping under air test to VAV 1-10
10/30/23: 8" chill water phase 1 to AHU 1 supply and return under test 100psi.
11/09/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return

8/21/23: L0300 all VAV hydro tested

9/20/23: hydronic piping under air test from main entrance to D0300 run offs ok to insulate
10/20/23: hydronic piping under pressure from main entrance to D0300 feeding all VAV's
11/9/23: hydronic piping under pressure 6" chill water mains corridor iso valve to ahu 3.
12/11/2023 COT - HCME - Hydronic Piping  Partial Pass 6/29/23. Piping in room L0300.

7/10/23 Piping in room L0200

7/13/23. Corridor K400

7/24/23: Hydronic piping from air handler one to main corridor. Supply and return

8/21/23: L0300 all VAV hydro tested

9/20/23: hydronic piping under air test from main entrance to D0300 run offs ok to insulate
10/20/23: hydronic piping under pressure from main entrance to D0300 feeding all VAV's
11/9/23: hydronic piping under pressure 6" chill water mains corridor iso valve to ahu 3.
12/11/23: Hydronic piping under pressure feeding all VAV's in A0300 and B0300.
12/14/2023 COT - HCME - Hydronic Piping  Partial Pass 7/24/23: Hydronic piping from air handler one to main corridor. Supply and return
8/2/23: Hydronic piping from main to G0300 under air test ( asking to insulate)
8/25/23: not ready
8/29/23: hydronic piping under air test from L0200 to K0200 (VAV 1-21, 1-22, 1-29, 1-30, 1-25)
10/4/23: Hydronic piping under air test to VAV 1-10
10/30/23: 8" chill water phase 1 to AHU 1 supply and return under test 100psi.
12/14/23: VAV 3-18 AND VAV 3-19 UNDER HYDRONIC TEST. 100PSI