Inspection Status: Passed

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
01/08/2026 COT - HCBU - Building Progress Passed 1-8-26: approved.
09/26/2025 COT - HCBU - Building Progress Re-inspection required 9-26-25: add shot pins 12" o.c. at sill and shot pins at top track-see schedule for details.
10/07/2025 COT - HCBU - Building Progress Partial Pass Sheetrock nailing on West walls. Ok to tape progress areas.
10/08/2025 COT - HCBU - Building Progress Partial Pass 10-8-25: drywall nailing on demising wall from upper decking to approximate 10' AFF verified and approved. Contractor will schedule remaining section of drywall nailing at a later date. Okay to tape & texture progress areas.
10/23/2025 COT - HCBU - Building Progress Partial Pass 10-23-25: partial pass on drywall nailing- end of wall still needs drywall. Okay to proceed with tape & texture at progress areas.
10/30/2025 COT - HCBU - Building Progress Partial Pass 10/30/25 ceiling kickers framing per plan, ok to proceed in suite
11/13/2025 COT - HCBU - Building Progress Partial Pass 11-13-25: in wall electrical domestic & dwv under test. Okay to drywall progress areas.
11/17/2025 COT - HCBU - Building Progress Re-inspection required 11-17-25: add nails at joints- spacing not per code. See- Code for details.
11/19/2025 COT - HCBU - Building Progress Partial Pass 11/19/2025 Drywall screw inspection approved.
11/25/2025 COT - HCBU - Building Progress Partial Pass 11/25/2025 partial pass. Screw inspection approved on demising wall. North and east ends.
12/01/2025 COT - HCBU - Building Progress Partial Pass 12-1-25: RFI showing demising wall bracing at 20' o.c. has been submitted to the city for review. Okay to drywall upper section to bottom of decking at own risk. Schedule a screw inspection prior to tape & texture.
12/09/2025 COT - HCBU - Building Progress Canceled 12-9-25: canceled by contractor.
12/10/2025 COT - HCBU - Building Progress Partial Pass
12/11/2025 COT - HCBU - Building Progress Partial Pass 12-11-25: okay to tape remaining section of drywall.
12/16/2025 COT - HCBU - Building Progress Partial Pass 12-16-25: okay to tape/texture remaining walls of suite 160.