Parcel: 138241600


Addresses:

1681 W VALENCIA RD


Inspection Status: Re-inspection required

Inspection History: COT - HCBU - Framing

Permit Number - TC-COM-0325-00519

Inspection Description - COT - HCBU - Framing

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
08/13/2025 COT - HCBU - Framing Re-inspection required 8-13-25: framing courtesy inspection- as contractor began renovating,he discovered termite damage to posts, cripple studs, studs, damaged truss, plumbing, mechanical, and electrical concerns. A structural engineer is required to determine the structural integrity of the site and revisions will be required to address many of these issues. Additionally, anything not documented in the approved plans must be addressed in the revisions and approved by the city.
08/19/2025 COT - HCBU - Framing Partial Pass 8-19-25: inspected interior framing along the south side of TI only-add washers & anchor bolts 32" o.c. for exterior walls where plans calls for masonry veneer. Shim all studs that are not making contact with either mud sill or top plates. Firefoam all penetrations at top plates, submit RFI on girder fix and the required Simpson ties located on south side of building and include mention of cripple studs & studs that were sistered. Reinspection required but okay to continue with TI at progress areas.
09/02/2025 COT - HCBU - Framing Partial Pass 9-2-25: exterior furr out on east side of building & nailing verified per plans-okay to continue with construction. Parapet framing/sheathing approved-okay to continue at progress areas at own risk pending RFI approval.
09/11/2025 COT - HCBU - Framing Re-inspection required 9-11-25: provide an engineer fix letter for damaged truss at dining room. Add missing hold-down at the wall dividing the new addition located at the north western section of building-see plans for details. Add anchor bolts to marked locations- anchor bolts must be installed in the middle-third of sill plate. Have architect submit required revisions mentioned on previous inspections from 8/13, 8/19, and 9/2.
09/16/2025 COT - HCBU - Framing Partial Pass 9-16-25: verified anchor bolt spacing & hold-downs per plans. Okay to continue with construction at progress areas to include, new addition area. See notes: regarding truss fix at dining room area.
10/16/2025 COT - HCBU - Framing Partial Pass 10-16-25: drywall nailing at kitchen areas approved. Okay to tape & texture progress areas.
10/22/2025 COT - HCBU - Framing Partial Pass 10-22-25: partial pass for framing at bathrooms. Okay to continue with construction at own risk pending city approval on RFI.
10/27/2025 COT - HCBU - Framing Partial Pass 10-27-25: drywall nailing for bathrooms and kitchen area approved. Okay for tape & texture at progress areas.