Inspection Status: Not Ready
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 08/22/2025 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
8-22-25: not ready. |
| 08/25/2025 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
8-25-25: not ready. |
|
COT - HCEL - Electrical Intermediate |
|
Re-inspection required |
9-11-25: in wall dining room receptacles verified-okay to cover walls in dining room only. Firefoam penetrations at marked locations, finish securing conduct to walls and provide supports conduits lying on grid. A large majority of electrical wiring from inside building was gutted/removed & a menu board not on plan was added. An updated electrical plan/schedule must be submitted to the city for review & approval. |
| 09/16/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
9-16-25: construction is continuous-pending updated electrical schedule/plan. |
| 09/26/2025 |
COT - HCEL - Electrical Intermediate |
|
Re-inspection required |
9-26-25: called contractor& left voicemail at 615am. I waited until 625 and left because there was no access to building. |
| 09/26/2025 |
COT - HCEL - Electrical Intermediate |
|
Re-inspection required |
9-26-25: submit an electrical RFI with an updated plan/schedule. An additional RFI shall be submitted to the city for review addressing ADA compliance on each restroom. |
| 10/08/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
10/8/25: electrical at kitchen area approved at risk that revision gets submitted prior to final and approved. Pending panels and bathrooms. |
| 12/23/2025 |
COT - HCEL - Electrical Intermediate |
|
Passed |
|