Date Description Inspector Results Comments
01/26/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 01/26/2026
Partial pass pending other progress areas. Verified 170ft run of 36" depth trench with (2) 1.5" & (3) 1" schedule 40 conduit. Okay to backfill with shading and caution tape.
01/27/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 01/27/2026
Partial pass. Verified 90' run of (1x) 1.5" & (1x) 1" schedule 40 conduit in 36" trench to Christy box in between. Okay to backill with shading materials.