Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 05/31/2024 |
BULD - Electrical Clearance |
|
Partial Pass |
This is a partial pass so that TEP can de-energize the panel at the transformer; so contractor can remove wires and repair damaged conduit from transformer to electrical panel. |
| 06/15/2024 |
BULD - Electrical Clearance |
|
Passed |
|