Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
07/09/2024 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024
07/10/2024 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024
7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas.
07/11/2024 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024
7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas.
7/11/24: 4th lift at elevator shaft reinforcement per plan, third party inspection report approved. Ok to proceed
07/12/2024 COT - HCBU - Masonry Pregrout  Passed Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024
7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas.
7/11/24: 4th lift at elevator shaft reinforcement per plan, third party inspection report approved. Ok to proceed
7/12/24: top out passed reinforcement per plan ok to grout.