Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - TC-COM-0324-00430
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024 | |
07/10/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024 7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas. |
|
07/11/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024 7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas. 7/11/24: 4th lift at elevator shaft reinforcement per plan, third party inspection report approved. Ok to proceed |
|
07/12/2024 | COT - HCBU - Masonry Pregrout | Passed | Elevator shaft 7’4 lift. Grid line: 18A-18B/A-A1. #5 vertical per plan and ladder ties at every other course. Okay to grout. 7/9/2024 7/10/24: 3rd lift at elevator shaft reinforcement per plan. Third party inspection report attached under attachments. Ok to grout progress areas. 7/11/24: 4th lift at elevator shaft reinforcement per plan, third party inspection report approved. Ok to proceed 7/12/24: top out passed reinforcement per plan ok to grout. |