Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 10/09/2025 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
Partial pass. Call in with finals. 10/9/2025 |
| 10/16/2025 |
COT - HCBU - Building Above Ceiling |
|
Passed |
|
| 11/15/2024 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
Temporary light fixtures are installed and properly wired to roof trusses. All mechanical, electrical, and plumbing above ceiling is complete for phase 1 of project. Okay to proceed with ceiling tile installation on this phase of project. |