Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/03/2023 |
ENGR Engineering Final
|
|
Not Ready |
Additional ramp has been added to the exterior of the building, which blocks the pedestrian pathway from the other portions of the building to the trash and closure. This ramp needs to be submitted and approved by engineering and zoning, was for it can be inspected for the site. |
| 11/02/2023 |
ENGR Engineering Final
|
|
Partial Pass |
Ok for Level 4 TCO, Final C of O pending Approval DP for all changes |