Inspection Status: Not Ready
Inspection History: COT - FCON - Fire - Final
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - FCON - Fire - Final |
|
Not Ready |
Fire sprinklers and Fire Alarm need to be evaluated and extended into newly enclosed area. The new space/gym not allowed to be used until life safety systems provide appropriate coverage. |
| 01/04/2024 |
COT - FCON - Fire - Final |
|
Partial Pass |
Fire sprinkler need to be added to the sauna, Smoke detectors need to be re-installed in new gym and fire panel needs to be addressed, Fire extinguisher needs to be installed in the new gym. |
| 02/15/2024 |
COT - FCON - Fire - Final |
|
Passed |
|
| 01/05/2024 |
COT - FCON - Fire - Final |
|
Partial Pass |
Fire alarm deficiencies need to be addressed. Sauna not allowed to be used until fire sprinkler is added. OK to obtain TCO level 4 for new gym area. |