Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/05/2023 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7-5-23: Restrooms only. | |
| 08/29/2023 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 8-28-23: UG for restrooms. | |
| 09/11/2023 | COT - HCPL - Plumbing Intermediate | Canceled | 7-5-23: Restrooms only. 8-28-23: UG for restrooms. 9/11/23: inspection canceled per Alexis. |
|
| 09/12/2023 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7-5-23: Restrooms only. 8-28-23: UG for restrooms. 9/11/23: inspection canceled per Alexis. 9/12/23: men's restroom #135 plumbing intermediate approved. |
|
| 10/17/2023 | COT - HCPL - Plumbing Intermediate | Passed | 7-5-23: Restrooms only. 8-28-23: UG for restrooms. 9/11/23: inspection canceled per Alexis. 9/12/23: men's restroom #135 plumbing intermediate approved. 10/17/23: Room #136 plumbing intermediate approved. |