Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2026 | COT - HCBU - Building Progress | Partial Pass | 5-1-26: reinforcement for cmu Stair 2 approved- okay to grout 5th lift at 20'. Reinforcement for cmu walls at Stair 3 top out approved for 13th lift at 52' | |
| 05/07/2026 | COT - HCBU - Building Progress | Partial Pass | 5-7-26: Stair 2 cmu wall reinforcement approved. Okay to grout 8th lift at 32'. Note: please submit 7th lift 3rd party report to the city portal. |
|
| 08/27/2026 | COT - HCBU - Building Progress | Partial Pass | 8-27-26: 1st floor above ceiling drywall screw inspection at south wing corridor approved. | |
| 09/03/2026 | COT - HCBU - Building Progress | Partial Pass | 9-3-26: 2nd floor above ceiling drywall screw inspection at corridor approved for tape & texture. | |
| 09/10/2026 | COT - HCBU - Building Progress | Partial Pass | 9/10/26: 3rd floor south wing above ceiling drywall screw inspection was previously inspected & approved on 9/9/26- see "framing" notes. Okay to tape & texture progress areas. | |
| 09/11/2026 | COT - HCBU - Building Progress | Partial Pass | 9/11/26: 121-remove pex lines from wall, 125, 122- load bearing non-shear walls at anchor bolts with washers at 48" o.c...An anchor bolt is required within 12" from end of plates at intended wall fur out, 116, 115. Okay to fur out walls at room's 115, 116, 125. |