Inspection History Details
Inspection Status: Canceled
Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2026 | COT - HCPL - Plumbing Intermediate | Canceled | 7-14-26: canceled by contractor. | |
| 07/15/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7-15-26: 1st floor South wing rough plumbing inspected. Looked at nail guards, Boca plates, and supports. Add stud shoes to over notched framing members-non bearing walls up to 40% of stud's depth and 25% for exterior and load bearing walls. Will verify all items at intermediates. | |
| 09/03/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 9-3-26: 122, 123, 124, 126, 127, 128, 129, 232, 229, 230, 228, 227-washer stacker not under test, 226, 225, 224, 223-not ready, 323, 325, 324, 326, 327-washer box not under test,328, 329, 430, 431, 429-strap support dwv, 428-support dwv, 427-washer box not under test, 426, 425, 424. Add FHA plates where studs are over notched by more than 40 percent and either sister those studs or add a stud shoe. Fire caulk all penetrations at decking between floors and fire caulk penetrations at top plates. Reschedule inspection when corrections are made. | |
| 09/04/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 9-4-26: reinspected the DWV at units from inspection dated 9/3/26. All units were located on the south wing. Remaining units on northern section of south wing will be scheduled next week. The units inspected today were all verified under test and fire caulking complete at DWV top,plates and at decking only. No pex lines were tested at in wall and DWV above ceiling was not looked as well. These inspections will be scheduled in the near future. Load bearing studs may be over notched by while non load bearing studs 25 percent while non load bearing studs may be notched up to 40 percent. At Over notched studs at 2-4 floors be sure to install a stud shoe together with an FHA Plate. Over notched studs at the 1st floor shall have a sister stud together with an FHA Plate. Please submit engineers letter with this detail to the city & schedule an MEP/Framing inspection for units with intended furred out walls prior to drywall. Okay to continue with construction at progress areas. | |
| 09/08/2026 | COT - HCPL - Plumbing Intermediate | Canceled | 9-8-26:canceled at contractor's request. | |
| 09/10/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 9/10/26: Verified DWV only at in walls at room's 121, 120-add Boca plate to marked area, 119, 118, 117, 116, 115, 216, 217, 218, 219, 220, 221, 222, 316, 317-add stud shoe and add fha plate at laundry, 318, 319, 320, 321, 322-strap lavatory dwv, 417, 418-seal plate penetration, 419, 420, 421, 422- fha plate & stud shoe at laundry, 423. DWV at south wing corridors levels 1-4 verified under test. We will re-walk units that were noted for corrections. Note: Per C404.4 of the IECC, Hot pex lines 1" and less require that they be insulated at in walls and above ceiling regardless of whether in a conditioned or unconditioned space. |
|
| 10/06/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 10/6/26: add supports for exhausts at 4' intervals at each unit inspected & missing bathroom exhaust tie-in/see previous notes, laundry exhausts too long -does not meet code requirements-possible RFI for installation of a fan, 129, 128-fire caulk penetrations at south wall at bedroom, seal exterior wall penetrations, 127, 126-dwv penetration at south party wall, 125, 124, 123, 122-seal party wall penetrations. Per C404.4 of the IECC, requires that 1/2 hot pex lines be insulted-add insulation to pex lines in wall & above ceiling. Note: mechanical not ready. |
|
| 10/16/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 10/16/26: MEP 2nd floor Southwing Unit's 230-, provide RFI for post adjacent to window, add stud to exterior wall at marked location-seal top plate of DWV at laundry, tie in sprinkler, insulate hot leg of copper, seal penetration at decking, laundry exhaust length does meet code-submit RFI fix on all A units, 228- add a strap to duct at marked location, seal penetration at party wall, seal DWV at decking-top & bottom, add insulation to copper line, fha plates required at top plates of load bearing walls, add mechanical tape to flex, seal exterior wall to- plates, 229- missing hanger, fha plate, 226-seal DWV at decking in restroom, tie in sprinkler, seal penetrations at marked locations, add fha plates at top plates where DWV & exhausts penetrate, 224-fha at load bearing walls, add stud to marked area at exterior wall, add nail guards to marked locations, insulate hot leg of copper line, 223-tie in sprinkler, tie in condensation line, insulate hot leg of copper line, fha plates required top & bottom of all load bearing walls, 229-Boca plates where top plates are over notched more than 50 percent, stud required at south west corner-over notched, 227-2x6 king and exterior studs at southwest corner & structural plates, 225-seal penetrations, insulate hot copper line, secure low voltage. |