Inspection Status: Canceled
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 07/14/2026 |
COT - HCPL - Plumbing Intermediate |
|
Canceled |
7-14-26: canceled by contractor. |
| 07/15/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
7-15-26: 1st floor South wing rough plumbing inspected. Looked at nail guards, Boca plates, and supports. Add stud shoes to over notched framing members-non bearing walls up to 40% of stud's depth and 25% for exterior and load bearing walls. Will verify all items at intermediates. |