Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 03/06/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
3/5/26: partial pass for pour 2. Ok to proceed with concrete placement. Reinforcement and PT observed and installed per approved plans. |
| 03/12/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
3/12/26: reinforcement and pt per approved plans at pour 3 |
| 03/16/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
3/16/26: reinforcement and pt per approved plans at pour 4 |
| 03/19/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
3/19/26: reinforcement per approved plans ok to proceed with pour 5 |
| 03/24/2026 |
COT - HCBU - Preslab |
|
Re-inspection required |
3-24-26: Tie off ends of reinforcement between pour 4& 5, missing diamond dowel at pour 3 &4-remove all loose debris at both footings and add chairs at various locations. |