Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2026 | COT - HCBU - Framing | Partial Pass | 6-11-26: Verified hangers Corridor's A,B, and C. Okay to continue with framing at progress areas. | |
| 08/10/2026 | COT - HCBU - Framing | Partial Pass | 8/10/2026 partial pass. Verified crickets in place at south west building. Okay to proceed with progress areas. | |
| 08/27/2026 | COT - HCBU - Framing | Partial Pass | 8-27-26: 1st floor interior shear/straps units 129, 127, 125-install anchor/washer in middle third of plate at marked location, 123-add anchor bolts at marked locations/ several areas marked where ab need to be installed in middle third of plate, 121, 119-add anchor bolts/washers at marked location, 116, 115-anchor bolt at marked location, mailbox northwest corner. Strap & shear nailing at listed units approved. Pending draftsop & fire caulking at penetrations | |
| 09/09/2026 | COT - HCBU - Framing | Partial Pass | 9-9-26: 3rd floor ceiling drywall screw approved for tape & texture. Strap & shear 2nd floor south wing room's 216, 217, 218, 220, 222, 224, 228, 230. Add nails to sill plate per either SW3 or SW4-see plans for more. I will re-walk nailing for sill plates at upcoming inspection. Splices at top plates for listed above rooms together with straps approved. | |
| 09/10/2026 | COT - HCBU - Framing | Canceled | 9/10/26: canceled per contractor. | |
| 09/18/2026 | COT - HCBU - Framing | Partial Pass | 9/18/2026 Partial pass. Plumbing walls original 2x at bathroom locations up to shower wall 2nd floor unit 230, 226, 223, 220, 218, 216. 3rd floor 316, 318, 320, 323,(add California stud along with stud shoe) 324, 326, 329, 330. Okay to cover up and furr out walls at all progress areas. Note; dryer boxes are approved and listed without having a 5 sided box around it. |
|
| 09/23/2026 | COT - HCBU - Framing | Partial Pass | 9/23/2026 Partial pass. South Wing, 1st Floor Anchor Bolts. Verified anchor bolts at party walls. Per 48” o.c with washer plates in place. Units 117,118,120,122,124,126. Approved. | |
| 09/25/2026 | COT - HCBU - Framing | Partial Pass | 9/25/26: 1st floors corridor's A,B,C above ceiling framing only verified. Okay to continue with construction at progress areas | |
| 10/02/2026 | COT - HCBU - Framing | Partial Pass | 10/2/26: 4th floor sill plate at shearwalls approved at south wing. 1st floor strap and shear approved at north wing(2nd floor has incorrect straps), 1st and 2nd wing approved for strap and shear at north wing south face. Pending anchor bolt and holdowns inspection. | |
| 10/02/2026 | COT - HCBU - Framing | Partial Pass | 10/2/26: Framing at elevator 1st and 2nd floor south and north face per approved plans wall type H and H1. | |
| 10/05/2026 | COT - HCBU - Framing | Partial Pass | 10/5/26: South WIng 4thFloor Behind Wall 431,430,429,427,425,424,421,419,417 approved. Ensure that structural straps are installed where over notching/boring occurs at top plate. FHA REQUIRED AT MULTIPLE LOCATIONS. | |
| 10/12/2026 | COT - HCBU - Framing | Re-inspection required | 10/12/26: 1st floor south wing-128-add shot pins at metal sill plate 6" within the ends of a plates, 129-add anchor bolt within 12" at the northeast corner of exterior wall, 127-add screws top & bottom at metal framing -kitchen wall, add shot pins at marked areas-shot pin shall be installed in middle third of plate, 126-add screws to metal framing at marked areas, 124, 123-add screws at marked areas of kitchen metal framing. Have architect/engineer of record submit an RFI-shot pin tighten bolt schedule for interior framing at load bearing walls, non-load bearing walls, corridor and at metal framing. | |
| 10/14/2026 | COT - HCBU - Framing | Partial Pass | 10/14/26: partial pass for interior framing, shot pins and anchor bolts at exterior walls for room's 122-129 verified. Pending architect's letter for metal framing details-seal penetrations at room 129's south wall-area marked with today's date. | |
| 10/15/2026 | COT - HCBU - Framing | Re-inspection required | 10/15/26: 115-RC Channel not on 12" o.c., add shot pins to marked locations, and anchor bolt to marked area, remove all electrical wires/mechanical from RC channels above ceiling, interior load bearing party walls-add anchor bolts at 48" o.c.,117-shot pins to marked locations, anchor bolts to marked area, RC Channel screws at marked areas, insulate hot copper line at marked location, 120-missing RC Blocking and screws at marked locations, anchor bolts to marked locations, RC channel screws, note not all areas marked, add blocking and screws to RC, add RC screws at 12" o.c., add support to exhaust at marked locations, insulate hot copper line. 121-RC Connelly screws at marked locations, insulate hot copper line, add screws to drywall at end of walls, 118-RC at marked locations. 119-RC channels, insulate hot copper lines. Note: unit's 122-129 not walked, however, insulate hot copper line and verify anchor bolts at interior load bearing party walls. Insulate all hot copper lines and make sure to add 10 mil tape where copper is in contact with other metals. |