Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-1-26: reinforcement for cmu walls at elevator, stair 1& stair 3 verified per plans . Okay to grout 1st lift at 4'. | |
| 04/07/2026 | COT - HCBU - Masonry Pregrout | Canceled | 4-7-26: canceled by contractor. | |
| 04/09/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4/9/26: 2nd lift at stair 1 and 2 and elevator approved | |
| 04/13/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 5/13/26: 3RD LIFT AT STAIR 3 AND 2 + Elevator approved. Ok to proceed with grout placement. | |
| 04/15/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-15-26: reinforcement for Stair 1 & 3 approved-okay to grout 4th. lift at 16'. Stair 2-ply to grout 2nd lift at 8'. | |
| 04/17/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4/17/26 partial pass for next lift at stairs 1 and 3 plus elevator | |
| 04/20/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4/20/2026 partial pass. 6th lift for perimeter walls at stairs 1 & 3 along with elevator shaft. 3rd lift for perimeter walls at stairs 2. Okay to grout all progress areas. |
|
| 04/21/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4/21/2026 approved per third party. 7th lift for perimeter at stairs 1 & 3 along with elevator shaft. | |
| 04/22/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-22-26: reinforcement at Stair 3 verified per plans. Elevator & Stair 1 verified by 3rd party. Okay to grout 8th. lift @ 32'. | |
| 04/24/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-24-26: reinforcement at Stair 2 verified per plans-okay to grout 4th lift at 16'. Reinforcement for Stair 1, 3, and elevator verified per 3rd party. Okay to grout 9th lift at 36'. | |
| 04/28/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-28-26: reinforcement at CMU walls for Stair's 1, 3, and elevator shaft are okay to grout 11 lift at 44'. | |
| 04/30/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 4-30-26: 12th lift at 48' for cmu walls of Stairs 1 & elevator shaft (top out)and stairs 3. | |
| 05/05/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 5/5/2026 6th lift 20’-24’ for perimeter cmu walls of stair 2 approved per third party report. Okay to grout progress areas. | |
| 05/08/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 5/8/2026 partial pass. Stair 2 8th Lift perimeter cmu walls approved. Okay to grout all progress areas. | |
| 05/11/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 5-11-26: Reinforcement at Stair 2 CMU walls verified per plans. Okay to grout 9th lift at 36'. | |
| 05/12/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 5-12-26: reinforcement for Stair 2 @ top out at 44' approved. | |
| 06/18/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 6-18-26: inspection for reinforcement/masonry lintel at CMU wall regarding RFI 41 Elevator Hoist way. Submit RFI to the city for review/approval together with 3rd party report. Any work reference RFI will be at own risk-pending city approval. | |
| 06/23/2026 | COT - HCBU - Masonry Pregrout | Not Ready | 23.26 Called : Don Vigil, phone number: (520) 989-1618. No answer, left voicemail. Drove to site and it was locked |
|
| 06/24/2026 | COT - HCBU - Masonry Pregrout | Partial Pass | 6-24-26: Reinforcement at elevator shaft CMU walls (top out @48') verified per S4.11 Detail 117, S5.13/249, S5.15/297. Okay to grout progress areas. Note: if you haven't done so already please submit this revision to the city for review/approval. |