Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Plumbing rough soil: West side of structure Northeast to,Southwest; 8” sewer lines to 4” lines and 4” lateral lines at approximately 225 feet. Ok to cover progress areas. |
| 02/20/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
2/20/26: Plumbing rough soil: east side of structure Northwest to, Northeast; 8” sewer lines to 4” lines and 4” lateral lines at approximately 225 feet. Ok to cover progress areas. |
| 09/09/2026 |
COT - HCPL - Plumbing Progress |
|
Canceled |
9-9-26: canceled by contractor. |
| 11/05/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
11/5/26: east wing 1st & 2nd floor DWV verified under test-Add straps at for 2 DWV vents at corridor-see marked areas. Also, lower verticals supports of DWV to 4'-see marked locations. Pending corrections and remaining floors. |
| 11/10/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
11/10/26: 3rd & 4th floor units, supports, fha plates, Boca plates, corridor, and laundry room at 4th floor verified under test, 309-provide a vertical support for laundry DWV, 415-fire caulk penetration around decking at laundry stack and fire caulk corridor/unit 415's south wall. Make corrections for both units but okay to continue at progress areas. |