Inspection Status: Partial Pass

Inspection History: COT - LCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
03/18/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 3-18-25, underground plumbing, Schedule 40 as per plans. Okay to backfill.
03/21/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 3-21-25, charlotte piping installed for underground plumbing-verified under test and per plans. Okay to backfill and continue with construction.
05/23/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 5-23-25: verified approximately 200' of 4" SDR35 sewer pipe under test & per plan. Okay to backfill with shading materials.
07/10/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 7-10-25: verified utility crossing/tapping from 6" fire service line. A 2"domestic line will be installed 5' from fire service line leading to new warehouse from Building 8. A pressure test will be performed at later date-okay to backfill progress areas.
07/16/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 7-16-25: 2" copper line stemming from building 8 to new construction verified per plans. Okay to backfill approximately 40' of open trench.
07/18/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 7-18-25: verified depth on 2" water line from shutoff valve to building under construction. Okay to backfill approximately 300' of open trench-shading required.
07/30/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 7-30-25: verified backflow preventer located between Building 8 and Building 11. Testing will conducted when meter is installed.
08/21/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 8-21-25: in wall domestic and DWV verified under test. Okay to continue with construction at progress areas.
10/31/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 10-31-25: partial pass for above ceiling grid framing.
11/12/2025 COT - LCPL - Plumbing Intermediate  Partial Pass 11-12-25: partial pass pending meter installation & pressure test.
12/16/2025 COT - LCPL - Plumbing Intermediate  Canceled 12-16-25: canceled by contractor.
12/23/2025 COT - LCPL - Plumbing Intermediate  Passed 12-23-25: plumbing intermediate approved.