Inspection Status: Partial Pass
Inspection History: COT - LCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 03/28/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
3-28-25, reinforcement per plan-preslab approved. Okay to pour concrete. |
| 04/16/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
4-16-25, masonry pre grout for cmu wall. Reinforcement per plans-okay to grout 3rd. lift at 12'. |
| 07/15/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
7-15-25: reinforcement on preslab for canopy verified per plans. Okay to pour concrete |
| 08/25/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
8-25-25: reinforcement verified per plan at Gridline 6-11/C-X. Okay for concrete placement at progress areas. |
| 08/27/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
8-27-25: reinforcement verified per plan at Gridline 11-20/X-CC & 22-26/I-J. Okay for concrete placement at progress areas. |
| 09/15/2025 |
COT - LCBU - Preslab |
|
Partial Pass |
9-15-25: reinforcement for light pole cage verified per plans-okay to pour concrete. |
| 09/30/2025 |
COT - LCBU - Preslab |
|
Passed |
9-30-25: all preslab on project approved. |