Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 02/21/2025 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial underground 2"communication conduit from existing building to new warehouse, and underground electrical conduits within the building pad and to the new storage yard location, okay to backfill progress areas |
| 08/04/2025 |
COT - LCEL - Electrical Underground |
|
Canceled |
by contractor |
| 08/14/2025 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
8-14-25: verified 6 electrical conduit stub outs on southwest side of Building 11. Okay to backfill progress area. |
| 09/03/2025 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
9-3-25: verified a 3" schedule 40 electrical conduit for SES at Building 8. Okay to backfill approximately 15' of open trench. |
| 11/12/2025 |
COT - LCEL - Electrical Underground |
|
Passed |
11-12-15: approved. |