Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Progress  

Date Description Inspector Results Comments
06/24/2025 COT - LCEL - Electrical Progress   Partial Pass 6-24-25: in wall rough electrical along interior side of cmu walls verified per plans. Okay to continue with construction at progress areas.
08/06/2025 COT - LCEL - Electrical Progress   Partial Pass 8-6-25: Schedule 40 primary/secondary conduits from Building 8 to Building 11 verified per plans. Okay to backfill open trench of approximately 200'.
08/06/2025 COT - LCEL - Electrical Progress   Partial Pass 8-6-25: verified trench depth on 2-1 1/4" and 1-3" primary/secondary Schedule 40 electrical conduits-okay to backfill approximately 130' of open trench. In wall electrical verified per plans. Okay to continue with construction at progress areas.
09/08/2025 COT - LCEL - Electrical Progress   Partial Pass 9-8-25: verified in wall insulation-okay to continue with construction at progress areas.
09/17/2025 COT - LCEL - Electrical Progress   Partial Pass 9-17-25: partial pass on drywall nailing-drywall installation not complete. Add nails along baseboard and schedule out remaining areas when complete. Verified hard duct as per plans. Okay to continue with construction at progress areas.
09/18/2025 COT - LCEL - Electrical Progress   Partial Pass 9-18-25: drywall nailing approved.
10/15/2025 COT - LCEL - Electrical Progress   Partial Pass 10-15-25: okay to continue with TI at hard lid areas together with office rooms.
Note: all junction boxes above ceiling must be labeled and will be inspected at upcoming inspection.
10/20/2025 COT - LCEL - Electrical Progress   Partial Pass 10-20-25: verified insulation above ceiling at hard lid areas. Okay to continue with construction at progress areas.
10/24/2025 COT - LCEL - Electrical Progress   Partial Pass 10-24-25: verified insulation between the TGI's. Okay to continue with construction at progress areas.
11/12/2025 COT - LCEL - Electrical Progress   Passed 11-12-25: approved.