Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
Permit Number - TC-COM-0223-00705
Inspection Description - COT - HCBU - Framing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2024 | COT - HCBU - Framing | Partial Pass | ||
| 06/28/2024 | COT - HCBU - Framing | Partial Pass | ||
| 07/12/2024 | COT - HCBU - Framing | Partial Pass | ||
| 08/06/2024 | COT - HCBU - Framing | Partial Pass | 8/6/24 partial approval for interior walls first floor OK to one side only walls are not inspected at this time 8/6/24 Partial approval for restroom, exterior walls, ok to insulate and install shear first floor |
|
| 08/08/2024 | COT - HCBU - Framing | Partial Pass | 8/8/24 condensate and overflow for water heater on the south west classroom is not terminated outside and not supported, ok to insulate interior walls | |
| 08/13/2024 | COT - HCBU - Framing | Partial Pass | 8/13/24 partial approval for first and second floor wall framing OK to insulate and drywall | |
| 08/19/2024 | COT - HCBU - Framing | Not Ready | 8/19/24 not ready called for construction meeting | |
| 08/27/2024 | COT - HCBU - Framing | Partial Pass | 8/27/24 partial approval for hard lids at classroom entries first floor and building north and south entries OK to install drywall | |
| 09/13/2024 | COT - HCBU - Framing | Partial Pass | Partial approval for East facing exterior wall first floor and second floor Partial or approval for West facing exterior wall first and second floor Partial approval for South face the exterior wall and stair enclosure. OK to install sheeting 8/6/24 partial approval for interior walls first floor OK to one side only walls are not inspected at this time 8/6/24 Partial approval for restroom, exterior walls, ok to insulate and install shear 8/8/24 condensate and overflow for water heater on the south west classroom is not terminated outside and not supported, ok to insulate interior walls 8/13/24 partial approval for first and second floor wall framing OK to insulate and drywall 8/19/24 not ready called for construction meeting 8/27/24 partial approval for hard lids at classroom entries and building north and south entries OK to install drywall 9/13/14: hard lid framing at rooms 108,109, corrridor 101 and 106. |
|
| 09/18/2024 | COT - HCBU - Framing | Partial Pass | 9/18/24 alcove framing in all entry's and reception area on 2nd floor approved | |
| 09/24/2024 | COT - HCBU - Framing | Partial Pass | 9/24/24 partial approval above ceiling in rooms 208 and 209 ok to proceed | |
| 10/18/2024 | COT - HCBU - Framing | Passed |